I hired a contractor for a big project that includes a 400 square foot extension and a primary bathroom, but he walked off the job after starting late. We paid him in October, but he didn't begin work until January 13. Just two days into the project, he asked for a second payment, claiming he was at the halfway point. Now he wants to scrap the bathroom, only deduct $5,500, and is demanding an additional $20,000 to continue. He also threatens to leave if I don't agree to a new contract. His subcontractors have quit due to non-payment, and I can't get a clear breakdown of where my money has gone since he refuses to provide receipts. The site is a mess—broken steps, damaged yard, broken tiles, and holes in the ceiling. I've contacted the town and decided to stop working with him, but I'm unsure of my options. An attorney feels expensive and I'm hesitant—would they really help me get my money back? The architect who referred him wants to mediate for $2,500, but I'm skeptical about their support. What should I realistically do from here?
3 Answers
First off, stop all payments immediately, especially the second check if it hasn't been cashed yet. You need to protect yourself financially. If you can, consult a lawyer to see how much trouble you're in legally. It might also be worth reporting the contractor to the appropriate boards. They might take action that could help you, especially if he's acting unethically.
Honestly, it sounds like you've lost money with him. Be ready for subcontractors and suppliers to possibly come after you for what they’re owed too. Document everything and prepare your case if you end up needing to go to court or file complaints.
Dude, your best bet is to strictly review your contract. What does it say about payments and work completion? Also, consider going after his bond if he has one, as that’s what it's meant for in situations like this. Don't let them push you around. Have a plan before making any more payments.