Disputing Huge Unexpected Charges from My Contractor

0
Asked By CleverBee123 On

Hey everyone! I'm in a tough spot with my contractor after renovating my home. Initially, the bid for my addition was $303k, but at the end of the project, they handed me a bill with an additional $143k! They've added costs for things like $5k for extra dumpsters, $10k extra for cabinets they sent me to buy at Lowe's (which were actually on sale!), and even $4k more for gutters because I asked for a match to my existing ones. Not once did they mention these extra charges during the process. I'm really confused about how they expect me to just have an extra $143k! This company is well-known, and there were also issues with the quality of their work. I thought the contract stated it would cover the addition of gas to the fireplace, but they charged a lot more to move the lines without informing me. I'm feeling quite devastated by all of this. How is it even possible for them to do this?

3 Answers

Answered By RealTalkRaven On

That sounds super stressful. I think you're right to be concerned—they should have kept you in the loop about any extra work and costs. What kind of contract did you even sign? They might have a pretty shaky case if they didn’t get your approval for those charges.

SavvySquirrel42 -

Right? It’s insane that they’d expect you to cover that without telling you. If they didn't follow protocol for additional charges, that could really help your case.

Answered By FrustratedFox88 On

It sounds like you really need to get an attorney involved ASAP. Make sure you document everything, including the initial bid and any communications with the contractor. They should have notified you about additional costs before charging you. Check your contract to see what it says about extra charges; it might give you a leg to stand on.

SkepticalOwl44 -

Totally agree! Documentation is key here. If they've made promises or included costs in the original contract, they can't just slap extra charges on you.

Answered By CuriousCat567 On

What does your contract say about change orders? If they didn't provide you with change orders for that $143k, you're likely still locked into the original $303k. You might have a good case if they're adding costs without your approval!

HelpfulHound99 -

Exactly! If change orders weren't discussed or documented, then they can't just charge you willy-nilly. Definitely worth talking to someone who knows construction contracts.